Jati Tinggi Group
Jati Tinggi Group Berhad (Bursa ACE Market: JTGROUP, 0292) installs high- and medium-voltage underground and overhead cables, substations and landing stations — the power connections behind Tenaga Nasional’s grid and, increasingly, Malaysia’s data-centre campuses. Led by managing director Dato’ Seri Lim Yeong Seong; listed December 2023 at 27 sen.
Jati Tinggi wins RM33.1m 275kV link for Gerbil data centre
Jati Tinggi will lay two 275kV cable circuits and build a transition yard for interim power to the Gerbil data centre at Springhill, Port Dickson, in 9 months.
Jati Tinggi’s RM73mil 275kV job: the Banting data centre draws on Lion Group’s old Megasteel intake - RM142mil of power works for one campus is the price of getting on the grid
The Bursa filing behind Jati Tinggi Group’s third contract in a month calls it a "275kV PMU Megasteel cable connection to Consumer Landing Station No. 1" at Banting Tech Park, due …
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.