11 Nov 2026 · Updated 19 Nov 2026 · Policy · 4 min read

Data centres: 30% green power rule, one-year grid pledge

Energy Commission (Suruhanjaya Tenaga)Tenaga NasionalMalaysiaData CentresRenewable EnergyPlanning Policy
Scott Seow
Probationary Estate Agent · PEA 4428 · CID Realtors Sdn Bhd
Key takeaways
  • Data centres must use at least 30% renewable energy; the Energy Commission is writing the framework, with no start date yet.
  • TNB pledges to connect approved data centres to the grid within one year of approval.
  • States must confirm water supply before a data centre is approved, and 24 new applications are on hold.
  • Under CRESS, solar and other renewable developers pay a 14 sen/kWh grid charge, fixed for 10 years; buyers pay a separate 4 sen.
Quick answers

How much renewable energy must data centres in Malaysia use?

At least 30%, measured against their total capacity or energy consumption; the Energy Commission is writing the framework.

How fast will TNB connect a data centre to the grid?

TNB pledges to connect approved data centres within one year of approval by the ministry-chaired committee.

What is the CRESS system access charge in 2026?

14 sen/kWh for renewable developers under the CRESS Acceleration Package, fixed for 10 years for projects running by end-2028; buyers pay a separate 4 sen/kWh.

Can a data centre be approved without enough water?

No. The state must confirm water is available first, the trade minister said, even if land is available.

On this page · 5 sections
  1. Getting approved
  2. Getting connected
  3. Buying green power through CRESS
  4. Update, 19 November 2026: a bigger penalty for unused power
  5. What it means for owners and buyers

The government has approved a rule that data centres must use at least 30% renewable energy, Deputy Prime Minister Datuk Seri Fadillah Yusof, who is also Energy Transition and Water Transformation Minister, told the Dewan Rakyat on 27 October 2026. The share is measured against a data centre's total capacity or energy consumption. The Energy Commission (Suruhanjaya Tenaga) is writing the framework and guidelines, including rules on self-generation. No start date has been given.

With what TNB, the Energy Commission and the trade minister said around it, these are the rules a data centre project now faces.

Getting approved

  • Power check: every electricity application gets a technical assessment of whether the system can meet the demand projected by the National Energy Council, and of transmission and distribution capacity and the investment needed, Fadillah said. Operators are also urged to generate their own solar power
  • Water check: the state must confirm water is available before a project can be considered. "If a state does not have sufficient water, we cannot approve even if land is available," Investment, Trade and Industry Minister Datuk Seri Johari Abdul Ghani said on 28 October
  • On hold: 24 new applications are waiting while the government checks, with TNB, whether supply and reserve margins can cover the 117 data centres already approved. If not, it will look at off-grid options such as solar with battery storage
  • No subsidy: power for data centres will not be subsidised, and their supply is being kept separate from that of other industries. Johari also said every development must meet at least 30% local content

Of the 117 approved, 55 are running and 19 are being built, Johari said; if all were finished, demand could reach 23,000MW to 23,500MW.

Getting connected

  • One year: once a data centre has been approved by the ministry-chaired committee, TNB pledges to connect it to the grid within a year, its chief distribution network officer, Ahmad Sazree Abd Aziz, said in Singapore on 27 October
  • Before that: TNB's Green Lane Pathway had already cut connection times from 36 months to as little as 12, with 33 projects delivered under it by March 2026

Buying green power through CRESS

The Corporate Renewable Energy Supply Scheme (CRESS) lets a renewable energy developer sell power directly to a company through TNB's grid. The developer pays a system access charge.

ChargePaid byRate
System access charge, firm supply (Aug 2025)Developer20 sen/kWh, down from 25
Same, under the CRESS Acceleration Package (Sep 2026)Developer14 sen/kWh, fixed for 10 years
CRESS charge (current tariff period)Buyer4 sen/kWh
  • Who gets 14 sen: projects that start operating by 31 December 2028, on contracts of at least 10 years. The rate is fixed for 10 years from the start date, the Energy Commission said on 15 October. About 3GW of projects are in the pipeline
  • The buyer's 4 sen: it is charged on the buyer's electricity use and follows the regulated tariff. Fadillah said it was already in place and should not be added to the developer's charge and reported as an "18 sen" fee
  • Coming next: updated CRESS guidelines are due this month

Update, 19 November 2026: a bigger penalty for unused power

  • Ten times higher: the connected load charge, which penalises users whose peak demand falls short of the capacity they declared, has been raised from RM8.50 to RM89.64 per kW, Investment, Trade and Industry Minister Datuk Seri Johari Abdul Ghani said at a Bursa Malaysia event on 10 November, The Star reported. He said it targets "phantom demand", where developers reserve capacity TNB has planned for and then leave it unused
  • How it works: TNB charges it for six years after a medium- or high-voltage supply (1kV and above) is connected, five years for an upgrade. It applies in any month when the peak is below 85% of the declared demand in years one to four, or 75% in years five and six, and is charged on each kW of the shortfall
  • An example (our sums): a data centre that declared 100MW but peaks at 50MW in its first years falls 35,000kW short of 85%. That costs about RM3,137,400 a month at the new rate, against RM297,500 at the old one
  • Not yet in TNB's rates: TNB's connected load charge page still showed RM8.50 per kW on 19 November, and no start date has been given. Fadillah had told Parliament in a written reply in October that the charge had been increased, without giving the figure. Johari spoke about data centres; it is not yet clear whether the new rate also covers other medium- and high-voltage users such as factories
  • Other data-centre rates already in force: an Ultra High Voltage tariff since 1 July 2025 for data centres taking supply above 50kV, and a separate water tariff of RM5.30 to RM5.38 per cubic metre in Peninsular Malaysia since 1 August 2025, Fadillah said
Need help with your factory, plant or industrial land?

Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.

Related news