17 Nov 2026 · Investment · 3 min read

Epoch's 120MW Johor data centre: bank syndication delayed

Epoch DigitalIskandar PuteriData Centres
Scott Seow
Probationary Estate Agent · PEA 4428 · CID Realtors Sdn Bhd
Key takeaways
  • Syndication of a US$488 million (about RM1.9 billion) loan for Epoch Digital's EMY1 data centre in Nusa Cemerlang Industrial Park, Johor, has been delayed after a 2 November lender briefing and site visit did not take place, Bloomberg reported.
  • Lead arrangers HSBC, AIIB, SMBC and Bank of China have signed and committed their money; no withdrawal or building delay was reported.
  • The 20.4-acre freehold campus is designed for 120MW; the first 60MW is fully contracted to BytePlus and was nearly built in April 2026, with service due in the fourth quarter of 2026.
Quick answers

Where is Epoch Digital's data centre in Malaysia?

EMY1 is on 82,526 sq m (about 20.4 acres) of freehold land in Nusa Cemerlang Industrial Park, Iskandar Puteri, Johor, part of the Nusajaya Tech Park data centre cluster.

Who is the customer of Epoch's Johor data centre?

The AIIB says the first 60MW phase is fully contracted to BytePlus; Bloomberg named ByteDance, TikTok's owner, as the intended user.

How is Epoch's Johor data centre funded?

The AIIB put the cost at about US$870 million, with a syndicated loan of up to US$520 million or 60% of cost and equity for the rest; the AIIB itself approved up to US$125 million.

Banks have been slower than planned to join a US$488 million (about RM1.9 billion) loan for Epoch Digital's 120MW data centre campus in Nusa Cemerlang Industrial Park, Johor, Bloomberg reported on 16 November 2026, as cited by EdgeProp. The four lead arrangers, HSBC, the Asian Infrastructure Investment Bank (AIIB), Sumitomo Mitsui Banking Corp (SMBC) and Bank of China, have already signed the loan and committed their money. Only the step of bringing in more banks has slipped.

What was delayed

  • Lender briefing: an online presentation for prospective lenders set for 2 November did not take place, and neither did a site visit planned for the same week
  • Reason given: one person told Bloomberg that Epoch's management was not available on those dates. New dates are being arranged
  • What did not change: the report did not say any committed money was withdrawn or that building or start-up was delayed. Actis, HSBC and SMBC declined to comment, and Epoch did not respond

The campus

  • Name: EMY1 on Epoch's website; the AIIB calls it Project Mercury
  • Owner: Epoch Digital, a data centre company in the portfolio of the investment firm Actis. The borrower is Epoch Digital (MYLB) Ltd
  • Site: 82,526 sq m, about 20.4 acres, of freehold land in Nusa Cemerlang Industrial Park, Iskandar Puteri, part of the Nusajaya Tech Park data centre cluster. The AIIB says the land was amalgamated and transferred before it lent
  • Size: 80,166 sq m of floor space and 120MW of IT capacity, built in phases; the first phase is 60MW
  • Customer: the first 60MW is fully contracted to BytePlus, according to the AIIB. Bloomberg named TikTok owner ByteDance as the intended user
  • Progress: the AIIB's April 2026 summary said the project was nearly completed. Epoch's website gives the fourth quarter of 2026 as the ready-for-service date

The money

  • Total cost: about US$870 million, the AIIB estimated in April 2026
  • Loan: a syndicated loan of US$520 million or 60% of the project cost, whichever is lower, with equity paying the rest. Bloomberg's US$488 million is within that cap
  • AIIB's share: up to US$125 million, approved on 23 April 2026. The AIIB expects its last payout by April 2028

Power and water

  • Targets: a power usage effectiveness (PUE) of 1.35 and a water usage effectiveness (WUE) of 1.6 litres per kWh, with hybrid cooling and liquid-cooled racks of about 21kW each
  • What that means at full load (our arithmetic on those targets): the first 60MW would draw about 81MW from the grid and use about 2.3 million litres of water a day; the full 120MW, about 162MW and 4.6 million litres a day
  • Water plan: the AIIB says water needs have been coordinated with the supplier, and a water plan will look for other sources and water-stress risks

Its neighbours

Nusa Cemerlang Industrial Park, developed by Crescendo Corporation, has become one of Johor's data centre clusters. Digital Halo's JHB1 campus (20.46 acres, 120MW) and STT GDC's STT Johor 1 are being built there, and Microsoft has agreed to buy land in the park. All are on our list of data centres in Malaysia.

Nusa Cemerlang Industrial Park (in solid olive), where Epoch Digital's EMY1 campus sits. Map: EPIQ, via EdgeProp
Need help with your factory, plant or industrial land?

Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.

Related news