PDC Takes Full Control of BKIP2 in Byram After Three Failed Tenders
- The PDC board decided on 20 July 2026 to develop the 1,300-acre (526ha) BKIP2 in Byram itself, after three RFP tender rounds failed to appoint a master developer.
- PDC plans to release about 200 acres (80.9ha) of industrial land each year, keeping a three-to-five-year supply reserve for investors in the Batu Kawan growth corridor.
- BKIP2 land will be priced at current market value — acquisition under the Land Acquisition Act 1960 costs far more than the early-1990s Batu Kawan land, which cost only a few sen.
- The bridge linking the development area must be completed first before the park can take shape.
The Penang Development Corporation (PDC) will take full control of the proposed Batu Kawan Industrial Park 2 (BKIP2) in Byram, after three rounds of Request for Proposal (RFP) tenders failed to produce a master developer. The decision was approved by the PDC board of directors on 20 July 2026.
Chief Minister Chow Kon Yeow confirmed the move at a press conference after the Malaysian International Chamber of Commerce and Industry (MICCI) Northern Region Annual Luncheon Dialogue at St Giles Wembley Hotel in George Town on 30 July.
"In regards to BKIP2, it went to tender three times but was not successful due to various reasons, which is why PDC has decided to take charge of the project," he said. "The PDC board of directors have agreed to take full control of the development."
1,300 acres, released in phases
PDC will now develop its roughly 526ha (1,300-acre) landbank in Byram in phases, with plans to make about 80.9ha (200 acres) of industrial land available each year to meet demand from investors and other stakeholders.
According to Chow, the phased approach is designed to keep a sufficient industrial land reserve to meet investor demand over the next three to five years, as demand for strategically located industrial land continues to grow — particularly in the Batu Kawan growth corridor.
He also stressed that the bridge linking the development area must be completed first to support the overall development of the new industrial park.
Priced at today's market — not 1990s Batu Kawan prices
Chow was direct on cost: BKIP2 land prices will have to be calculated based on current market prices. Land for the new park is acquired under the Land Acquisition Act 1960 at present-day values — unlike the original Batu Kawan acquisitions of the early 1990s, when he said the land cost only a few sen.
Update, October 2026: PDC has settled SD Guthrie’s court challenge over 380 acres it compulsorily acquired in Byram in 2020, raising the compensation to about RM241 million, or about RM14.56 psf (our report).
Separately: Pulau Jerejak bridge to proceed
At the same press conference, Chow said the planned private-sector development on Pulau Jerejak is set to move forward, with construction of a bridge linking the island to the Queensbay area in Bayan Lepas set to begin. The project covers only a 32.3ha (80-acre) parcel previously jointly owned by UDA Holdings Berhad and PDC — not the entire island — and the bridge is expected to be completed by 2028 or 2029.
- The Star (30 Jul 2026)
- Buletin Mutiara (30 Jul 2026)
- Penang Today
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
SD Guthrie settles Byram land fight with PDC for RM241m
SD Guthrie and PDC have settled their five-year fight over 380 acres in Byram, Penang, lifting compensation by RM68m to about RM241m, or RM14.56 psf.
China’s S J leases 8.5 acres in Batu Kawan for US$70m plant
PEN S J Electronics, the Penang arm of China’s S J Electronics, is leasing about 8.5 acres in BKIP3 from PDC for a US$70m chip-materials plant with 1,000 jobs.
SD Guthrie sells 264 acres in Byram, Penang, for RM252.6m
SD Guthrie is selling 263.63 acres of its Byram estate to Nexis X for RM252.64m, one of three land sales RHB expects it to book in the last quarter of 2026.